ARCFE Group 12

In Progress

Jackson

27-49/51 Jackson Avenue, Long Island City, NY 11101

I-956F

Approved

I-526E

Approved

The Project

About Jackson.

The fund raised will be used towards the construction of a 14-story mixed-use condominium building, which consists of 76 residential units and one commercial unit. The building is located at 27-49/51 Jackson Avenue, LIC, NY 11101. The lot area is 8,000 SF and the gross construction floor area is approximately 91,000 SF. The first and second floor will have about 16,000 SF prime retail spaces.

Exit strategy: EB-5 funds will be paid back from the condo sales. Total sales revenue estimated to be $86M, which is 1.5 times the sum of construction loan and EB-5 amount.

Key Facts

Location
27-49/51 Jackson Avenue, Long Island City, NY 11101
Targeted Employment Area
Qualified for TEA
Minimum Investment
$800,000 USD
Developer
Strategic Capital (CSCEC U.S. subsidiary)
Era
RIA

In Depth

The full Group 12 story.

Qualified for TEA · Award-Winning Regional Center · Prime location

JACKSON

The fund raised will be used towards the construction of a 14-story mixed-use condominium building, which consists of 76 residential units and one commercial unit. The building is located at 27-49/51 Jackson Avenue, LIC, NY 11101. The lot area is 8,000 SF and the gross construction floor area is approximately 91,000 SF. The first and second floor will have about 16,000 SF prime retail spaces. From the third to the fourteenth floor are 76 condominiums units including studio, one-bedroom, two-bedroom, and three- bedroom units.

PRIME LOCATION WITH HIGH RENTAL DEMAND

LONG ISLAND CITY

The Jackson project is located at the center of Long Island City (LIC). LIC is New York's fastest growing neighborhood. Its recent growth has opened door to a vibrant mix of things to see and do. The area has one of the most highly accessible transportation hubs, including 8 different subway lines. It is also rich in cultural diversity and home to a large community of artists. LIC is packed with museums, theaters and art spaces, including the infamous MoMA PS1 - one of the largest contemporary art institutions in the country.

Rents in this area are competitive but not off-the-chart high like Manhattan, while geographically still managed to be close to the city. This makes LIC the ideal place for young professionals to live in and the highly profitable investment option for real estate investors.

Developer · SOME COMPLETED PROJECTS · DECADES OF HANDS-ON EXPERIENCE

JACKSON: Strategic Capital

Strategic Capital is the U.S. subsidiary of CSCEC.

CSCEC ranked 13th on Fortune 500 list, and 1st in its industry. The company was founded in 1982 and over the years, it branched out to 50 countries and regions all around the world. The U.S. subsidiary of CSCEC has completed many notable projects in the U.S., such as: New York City Hall, Brooklyn Navy Yard, Expansion of the Long Island Rail Road, etc.

TEA QUALIFIED

The Jackson Project qualifies for TEA despite the stricter regulations in the EB-5 Reform Bill that was passed on March 15th, 2022. Being qualified for TEA also means that the minimum investment amount per investor is lower. Per the new regulations, TEA projects are placed at $800k per investor, while non-TEA projects are placed at $1.05M.

EXIT STRATEGY

EB-5 funds will be paid back from the condo sales. Total sales revenue estimated to be $86M, which is 1.5 times the sum of construction loan and EB-5 amount.

Project Progress

Latest updates from the site.

Nov 2025

To date, the project has been completed and successfully received its Temporary Certificate of Occupancy (TCO) in September 2025.

The building is officially named “iCross LIC”. It has been met with an enthusiastic response in the rental market and is now fully leased.

May 2024

The units have all been framed, sheetrock has been commenced. All electrical and plumbing are in. Construction expected completion at the end of 2024.

Site Report Archive — iCross LIC

July 2023

Plumbing is underway throughout the building

Working on interior framing layouts and electrical riser

Exterior masonry is near completion

Trash chute is being installed

Elevator equipment is coming later this month

Curtain wall is in production

Apr 2023

Jackson Project Top Off

Dec 2022

Foundation completed on November 16th

Poured concrete on first floor on December 15th

Super structure phases going vertical

Utilities (water and sewage) brought in

Aug-Sep 2022

Early stages of foundation expected to be completed by end of Q4/2022

Gallery

Jackson in view.

Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery
Jackson — project imagery

Construction Progress

From the job site.

For illustration purpose only

Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress
Jackson — construction progress